MC (QCLNG) JV - Mt Alma QLD - Camp 5
 
 
Modular Movers have just completed expanding Camp numbers from 150 to 450 bedrooms as well as additional laundry and linen stores.
 
These buildings were relocated from Camp 2 over 400km away and all works were completed within 14 days! These works included decking and roofing systems between accommodation buildings and amenities.
 
Our experienced team including transport and trades contractors all worked as a complete unit with a common goal - Successfully meeting the Client's deadline to reaccommodate staff returning from R&R Break.
  
Works will include;
  • Transport of buildings and infrastructure
  • Site cranes
  • Building services
  • Piering of buildings
  • Electrical and plumbing (including sewerage treatment plant / water filtration plant / generators / fuel storage)
  • Additional plumbing, electrical and fire detection system reticulation for camp expansion

 

During July 2013, Modular Movers decomplexed, transported and installed 10 (4 bedroom) accommodation units. This was completed with less than 1 weeks notice over 1 weekend! This included decking and roofing systems between existing accommodation buildings to the new additions.

 

   
 